PL:Contract Management Plan

From ITERMAGwiki

(Difference between revisions)
Jump to: navigation, search
 
(6 intermediate revisions not shown)
Line 1: Line 1:
== Generalities ==
== Generalities ==
-
The '''Contract Project Management Plan''' is a document that describes the '''Contract Project''' management system used by a '''Contract Project Manager'''.  
+
The '''Contract Management Plan''' is a document that describes the '''Contract''' management system used by a '''Contract Manager'''.  
-
The objective of the '''Contract Project Management Plan''' is do define the approach to be used by the Contract Project Manager to deliver the intended scope of the Contract Project.
+
The objective of the '''Contract Management Plan''' is do define the approach to be used by the Contract Manager to deliver the intended scope of a Contract.
-
The Contract Project Manager follows the '''Contract Project Management Plan''' following input from the Consortium Programme Leadership.  
+
The Contract Manager follows the '''Contract Management Plan''' following input from the ITERMAG Project Leadership.  
-
The '''Contract Project Management Plan''' includes the following main aspects:
+
The '''Contract Management Plan''' includes the following main aspects:
* [[#Structure | Contract Structure]];
* [[#Structure | Contract Structure]];
* [[#Scope | Scope Management]];
* [[#Scope | Scope Management]];
Line 20: Line 20:
-
We go through these proposed components one by one for '''ITERMAG''' to determine whether they should be part of the '''ITERMAG''' [[PL:Project Management Plan |Consortium Programme Management Plan]] or not, and what the current status is.
+
We go through these proposed components one by one for an '''ITERMAG Contract''' to determine whether they should be part of the [[PL:Project Management Plan |ITERMAG Project Management Plan]] or not, and what the current status is.
[[#top|Go to top]]
[[#top|Go to top]]
-
== [[#Structure|Contract Project Management Structure]] ==
+
== [[#Structure|Contract Management Structure]] ==
-
Eeach Consortium Contract is structured as a '''Project''', and is a component of the Consortium Structure, as shown in the following figure.
+
Each ITERMAG Contract is structured as a '''Project''', and is a component of the ITERMAG Consortium Structure, as shown in the following figure. This structuring is not explicitly in the ITERMAG Consortium Agreement, but is left to management by the ITERMAG Project Leadership, under the approval of the ITERMAG Steering Committee.
-
[[image:Structure.gif]]
+
[[image:Structure.gif|350px|center]]
=== Context ===
=== Context ===
-
The Contract Project Management provides surveillance of a Contract Project. The Contract Project Management functions under the Consortium Programme Leadership. The Consortium Programme Leader reports to the Consortium Steering Committee.
+
The Contract Management provides surveillance of a Contract. The Contract Management functions under the ITERMAG Project Leadership. The ITERMAG Project Leader reports to the ITERMAG Steering Committee.
-
=== Contract Project Manager ===
+
=== Contract Manager ===
-
Each call for interest gives rise to a "Contract Project" for which a Contract Project Manager is nominated by the Consortium Programme Leadership. The Contract Project Manager develops a plan of action to generate an offer. In case of a contract being awarded, the Contract Project Manager is responsible for the correct execution of the Contract Project. The Contract Project Manager reports to the Consortium Programme Leader.
+
Each call for interest gives rise to a "Contract Project" for which a Contract Manager is nominated by the ITERMAG Project Leadership and approved by the ITERMAG Steering Committee. The Contract Manager develops a plan of action to generate an offer. In case of a contract being awarded, the Contract Manager is responsible for the correct execution of the Contract. The Contract Manager reports to the ITERMAG Project Leader.
[[#top|Go to top]]
[[#top|Go to top]]
== Scope ==
== Scope ==
-
The scope of an ITERMAG Contract Project is defined by a call for interest or call for tender which gives rise to the contract or F4E grant itself. Both are referred to as "Contracts". It is then reduced, if necessary, by the Consortium Programme Leadership and ultimately by the Steering Committee.
+
The scope of an ITERMAG Contract is defined by a call for interest or call for tender which gives rise to the contract or F4E grant itself. Both are referred to as "Contracts". It is then reduced, if necessary, by the ITERMAG Project Leadership and ultimately by the ITERMAG Steering Committee.
[[#top|Go to top]]
[[#top|Go to top]]
== Schedule ==
== Schedule ==
-
The scheduling of a Contract Project is handled under Primavera using the following independent contract schedules:  
+
The scheduling of a Contract is handled under Primavera using the following independent contract schedules:  
* Magnetics construction planning, strongly linked to the ITER IO planning
* Magnetics construction planning, strongly linked to the ITER IO planning
-
* Contract Project planning, independently generated for each '''Contract Project''' and linked to the Consortium Programme Planning
+
* Contract planning, independently generated for each '''Contract''' and linked to the Consortium Project Planning
[[#top|Go to top]]
[[#top|Go to top]]
== Tendering ==
== Tendering ==
-
The Consortium Programme Leadership is initially responsible for creating a proposal for responding to a call for interest or a call for tender. This Outline Offer includes:
+
The ITERMAG Project Leadership is initially responsible for creating a proposal for responding to a call for interest or a call for tender. This Outline Offer includes:
* the resource requirements for each Member
* the resource requirements for each Member
-
* a back-to-back agreement between Members to agree and guarantee these resources
+
* a back-to-back agreement (backing contract) between Members to agree and guarantee these resources
* the contract schedule
* the contract schedule
* the contract costs for each Member
* the contract costs for each Member
Line 57: Line 57:
After approval by the Steering Committee:
After approval by the Steering Committee:
-
* a Contract Project Manager is confirmed by the Steering Committee in collaboration with the Consortium Programme Leadership
+
* a Contract Manager is confirmed by the ITERMAG Steering Committee after proposal by the ITERMAG Project Leadership
* a full commercial offer is established
* a full commercial offer is established
-
* the offer is transmitted to the Steering Committee for final approval and ultimately submission to the client.
+
* the offer is transmitted to the ITERMAG Steering Committee for final approval and ultimately submission to the Client.
The process for handling a call for interest or a call for tender is illustrated in the figure below.
The process for handling a call for interest or a call for tender is illustrated in the figure below.
-
[[image:ProcCallten.gif]]
+
 
 +
[[image:ProcCallten.gif|350px|center]]
[[#top|Go to top]]
[[#top|Go to top]]
== Financial==
== Financial==
-
The Contract Project Manager creates a contract spending curve when creating a draft offer. The Contract Project Manager is subsequently responsible for maintaining records of all the costs incurred by all Members, and on comparing them with the predicted spending curve. Deviations which suggest a significant final
+
The Contract Manager creates a contract spending curve when creating a draft offer. The Contract Manager is subsequently responsible for maintaining records of all the costs incurred by all Members, and on comparing them with the predicted spending curve. Deviations which suggest a significant final
-
deviation from the original cost estimates (>5%) shall be immediately signalled to the Consortium Programme Leader.
+
deviation from the original cost estimates (>5%) shall be immediately signalled to the ITERMAG Project Leader.
-
Splitting of the revenu from a Contract will be on an uniform basis according to the Contract of Association.
+
Splitting of the revenu from a Contract will be on an uniform basis according to the ITERMAG Consortium Agreement.
[[#top|Go to top]]
[[#top|Go to top]]
== Quality ==
== Quality ==
-
The Contract Project functions respecting the Contract Project Quality Plan under the Consortium Programme Quality Management System. This Quality Plan presents the procedures and tools to ensure that the individual Contract Project Management Plan is correctly and traceably executed by the Contract Project Manager.  
+
The Contract functions respecting the Contract Quality Plan under the ITERMAG Project Quality Management System. This Quality Plan presents the procedures and tools to ensure that the individual Contract Management Plan is correctly and traceably executed by the Contract Manager.  
[[#top|Go to top]]
[[#top|Go to top]]
== Resource Management ==
== Resource Management ==
-
Human Resources are "assigned" to work for the ITERMAG Consortium and will either be allocated to the Consortium Programme Leadership or to a specific Contract Project Manager.
+
Human Resources are "assigned" to work for the ITERMAG Consortium and will either be allocated to the ITERMAG Project Leadership or to a specific Contract Manager.
-
Clear accounting of the allocated resources for a Contract Project will fall under "Finance".
+
Clear accounting of the allocated resources for a Contract will fall under "Finance".
-
Forward planning of the required and allocated resources will be generated by the Contract Project Manager.
+
Forward planning of the required and allocated resources will be generated by the Contract Manager.
Non-release of the required Human Resources is foreseen to be a major difficulty due to the extreme pressure on Human Resources in the Members.
Non-release of the required Human Resources is foreseen to be a major difficulty due to the extreme pressure on Human Resources in the Members.
[[#top|Go to top]]
[[#top|Go to top]]
== Communications ==
== Communications ==
-
Communications are partially described under '''[[#Structure|Project Structure]]''', and include internal and external communications.
+
Communications are partially described under '''[[#Contract Project Management Structure|Project Structure]]''', and include internal and external communications.
=== External communications ===
=== External communications ===
-
* Technical decisions: Client <--> Contract Project Manager, copied to Contract Project Team and Consortium Programme Leadership and archived.
+
* Technical decisions: Client <--> Contract Manager, copied to Contract Team and ITERMAG Project Leadership and archived.
-
* Technical information exchanges: Client <--> Contract Project Manager, copied to Contract Project Team and Consortium Programme Leadership and archived.
+
* Technical information exchanges: Client <--> Contract Manager, copied to Contract Team and ITERMAG Project Leadership and archived.
=== Internal communications ===
=== Internal communications ===
-
* Consortium Programme Leader --> Contract Project Manager, copied to Consortium Project Leadership and archived.
+
* ITERMAG Project Leader --> Contract Manager, copied to ITERMAG Project Leadership and archived.
-
* Contract Project Manager --> Consortium Programme Leader, coped to Consortium Programme Leadership and archived.
+
* ITERMAG Contract Manager --> ITERMAG Project Leader, copied to ITERMAG Project Leadership and archived.
Status --[[User:Jo|Jo]] 22:41, 25 April 2008 (CEST) The usage of the Wiki under development for ITERMAG is being evaluated as appropriate for archival. How to handle E-mail is under discussion.
Status --[[User:Jo|Jo]] 22:41, 25 April 2008 (CEST) The usage of the Wiki under development for ITERMAG is being evaluated as appropriate for archival. How to handle E-mail is under discussion.
[[#top|Go to top]]
[[#top|Go to top]]
 +
== Change Control ==
== Change Control ==
Change Control contains 3 elements:
Change Control contains 3 elements:
Line 105: Line 107:
=== Technical design changes ===
=== Technical design changes ===
-
* Client <--> Contract Project Manager, Design Change Request and cost/schedule impact signed on both sides after agreement, copied to Consortium Programme Leader and archived. The DCR clearly states all interfaces affected by the change. Consortium Programme Leader rejects or approves change and signs. If impact on cost-schedule is significant (TBD) final decision is deferred to Steering Committee by Consortium Programme Leader. The Design Change Decision is then archived.
+
* Client <--> Contract Manager, Design Change Request and cost/schedule impact signed on both sides after agreement, copied to ITERMAG Project Leader and archived. The DCR clearly states all interfaces affected by the change. ITERMAG Project Leader rejects or approves change and signs. If impact on cost-schedule is significant (TBD) final decision is deferred to ITERMAG Steering Committee by ITERMAG Project Leader. The Design Change Decision is then archived.
-
* Consortium Member --> Contract Project Manager, Design Change Proposal signed on both sides after agreement, to be submitted to Consortium Programme Manager for transmission to client if Contract Project Manager agrees.
+
* ITERMAG Member --> Contract Manager, Design Change Proposal signed on both sides after agreement, to be submitted to ITERMAG Project Manager for transmission to client if Contract Manager agrees.
=== Contract condition changes ===
=== Contract condition changes ===
-
* Contract Project Manager --> Consortium Programme Leader, Contract Condition Change is notified if performance, cost or schedule variations lead to conflict with the contract conditions. Consortium Programme Leader assumes responsibility.
+
* Contract Manager --> ITERMAG Project Leader, Contract Condition Change is notified if performance, cost or schedule variations lead to conflict with the contract conditions. ITERMAG Project Leader assumes responsibility.
-
* Client --> Consortium Programme Leader, Contract Condition Change is notified if technical changes are required by the client. Consortium Programme Leader evaluates the impact of the changes and reports to Steering Committee with a proposed action.
+
* Client --> ITERMAG Project Leader, Contract Condition Change is notified if technical changes are required by the client. ITERMAG Project Leader evaluates the impact of the changes and reports to ITERMAG Steering Committee with a proposed action.
=== Internal management changes ===
=== Internal management changes ===
-
* Member --> Steering Committee, Member reports any change in resources previously allocated.
+
* Member --> ITERMAG Steering Committee, Member reports any change in resources previously allocated.
-
Status --[[User:Jo|Jo]] 23:10, 25 April 2008 (CEST) The development of the change request system is intimately linked with the Quality Plan and appropriate procedures and forms will be proposed by the QA experts under request by the Consortium Programme Leader.
+
Status --[[User:Jo|Jo]] 23:10, 25 April 2008 (CEST) The development of the change request system is intimately linked with the Quality Plan and appropriate procedures and forms will be proposed by the QA experts under request by the ITERMAG Project Leader.
[[#top|Go to top]]
[[#top|Go to top]]
Line 125: Line 127:
Risks are assessed by:
Risks are assessed by:
-
* Contract Project Manager for a first technical and commercial view
+
* Contract Manager for a first technical and commercial view
-
* Consortium Programme Leadership to ensure a common technical and commercial view
+
* ITERMAG Project Leadership to ensure a common technical and commercial view
-
* Steering Committee to ensure a global financial and strategic view
+
* ITERMAG Steering Committee to ensure a global financial and strategic view
-
Decisions on risk as the authority of the Steereing Committee.
+
Decisions on risk are the authority of the ITERMAG Steering Committee.
[[#top|Go to top]]
[[#top|Go to top]]
 +
== Procurement==
== Procurement==
Procurement of external resources/material
Procurement of external resources/material

Latest revision as of 18:31, 28 June 2008

Contents

Generalities

The Contract Management Plan is a document that describes the Contract management system used by a Contract Manager.

The objective of the Contract Management Plan is do define the approach to be used by the Contract Manager to deliver the intended scope of a Contract.

The Contract Manager follows the Contract Management Plan following input from the ITERMAG Project Leadership.

The Contract Management Plan includes the following main aspects:


We go through these proposed components one by one for an ITERMAG Contract to determine whether they should be part of the ITERMAG Project Management Plan or not, and what the current status is.

Go to top

Contract Management Structure

Each ITERMAG Contract is structured as a Project, and is a component of the ITERMAG Consortium Structure, as shown in the following figure. This structuring is not explicitly in the ITERMAG Consortium Agreement, but is left to management by the ITERMAG Project Leadership, under the approval of the ITERMAG Steering Committee.

Structure.gif

Context

The Contract Management provides surveillance of a Contract. The Contract Management functions under the ITERMAG Project Leadership. The ITERMAG Project Leader reports to the ITERMAG Steering Committee.

Contract Manager

Each call for interest gives rise to a "Contract Project" for which a Contract Manager is nominated by the ITERMAG Project Leadership and approved by the ITERMAG Steering Committee. The Contract Manager develops a plan of action to generate an offer. In case of a contract being awarded, the Contract Manager is responsible for the correct execution of the Contract. The Contract Manager reports to the ITERMAG Project Leader.


Go to top

Scope

The scope of an ITERMAG Contract is defined by a call for interest or call for tender which gives rise to the contract or F4E grant itself. Both are referred to as "Contracts". It is then reduced, if necessary, by the ITERMAG Project Leadership and ultimately by the ITERMAG Steering Committee.

Go to top

Schedule

The scheduling of a Contract is handled under Primavera using the following independent contract schedules:

Go to top

Tendering

The ITERMAG Project Leadership is initially responsible for creating a proposal for responding to a call for interest or a call for tender. This Outline Offer includes:

This Outline Offer is submitted to the Steering Committee for modification or approval.

After approval by the Steering Committee:

The process for handling a call for interest or a call for tender is illustrated in the figure below.

ProcCallten.gif

Go to top

Financial

The Contract Manager creates a contract spending curve when creating a draft offer. The Contract Manager is subsequently responsible for maintaining records of all the costs incurred by all Members, and on comparing them with the predicted spending curve. Deviations which suggest a significant final deviation from the original cost estimates (>5%) shall be immediately signalled to the ITERMAG Project Leader.

Splitting of the revenu from a Contract will be on an uniform basis according to the ITERMAG Consortium Agreement.


Go to top

Quality

The Contract functions respecting the Contract Quality Plan under the ITERMAG Project Quality Management System. This Quality Plan presents the procedures and tools to ensure that the individual Contract Management Plan is correctly and traceably executed by the Contract Manager.

Go to top

Resource Management

Human Resources are "assigned" to work for the ITERMAG Consortium and will either be allocated to the ITERMAG Project Leadership or to a specific Contract Manager. Clear accounting of the allocated resources for a Contract will fall under "Finance". Forward planning of the required and allocated resources will be generated by the Contract Manager. Non-release of the required Human Resources is foreseen to be a major difficulty due to the extreme pressure on Human Resources in the Members.

Go to top

Communications

Communications are partially described under Project Structure, and include internal and external communications.

External communications

Internal communications

Status --Jo 22:41, 25 April 2008 (CEST) The usage of the Wiki under development for ITERMAG is being evaluated as appropriate for archival. How to handle E-mail is under discussion.

Go to top

Change Control

Change Control contains 3 elements:

Technical design changes

Contract condition changes

Internal management changes

Status --Jo 23:10, 25 April 2008 (CEST) The development of the change request system is intimately linked with the Quality Plan and appropriate procedures and forms will be proposed by the QA experts under request by the ITERMAG Project Leader.

Go to top

Risk

Assessment and management of risk is an integral component of the contract assessment on a case by case basis. Risks include:

Risks are assessed by:

Decisions on risk are the authority of the ITERMAG Steering Committee.

Go to top

Procurement

Procurement of external resources/material

Status --Jo 23:10, 25 April 2008 (CEST) Not yet considered.

Go to top

Personal tools
Namespaces
Variants
Actions
Navigation
Toolbox