PL:Contract Management Plan

From ITERMAGwiki

(Difference between revisions)
Jump to: navigation, search
Line 5: Line 5:
The objective of the '''Contract Project Management Plan''' is do define the approach to be used by the Contract Project Manager to deliver the intended scope of the Contract Project.
The objective of the '''Contract Project Management Plan''' is do define the approach to be used by the Contract Project Manager to deliver the intended scope of the Contract Project.
-
The Contract Project Manager follows the '''Contract Project Management Plan''' following input from the Consortium Project Leadership.  
+
The Contract Project Manager follows the '''Contract Project Management Plan''' following input from the Consortium Programme Leadership.  
Line 30: Line 30:
=== Contract Project Management ===
=== Contract Project Management ===
-
The Contract Project Management provides surveillance of a Contract Project. The Consortium Project Leader then reports to the Consortium Steering Committee.
+
The Contract Project Management provides surveillance of a Contract Project. The Consortium Programme Leader then reports to the Consortium Steering Committee.
=== Contract Project Manager ===
=== Contract Project Manager ===
-
Each call for tender gives rise to a "Contract Project" for which a Contract Project Manager is nominated by the Project Leadership. The Contract Project Manager develops a plan of action to generate an offer. In case of a contract being awarded, the Contract Project Manager is responsible for the correct execution of the Contract Project. The Contract Project Manager reports to the Consortium Project Leader.
+
Each call for tender gives rise to a "Contract Project" for which a Contract Project Manager is nominated by the Project Leadership. The Contract Project Manager develops a plan of action to generate an offer. In case of a contract being awarded, the Contract Project Manager is responsible for the correct execution of the Contract Project. The Contract Project Manager reports to the Consortium Programme Leader.
Scope --[[User:Jo|Jo]] 23:10, 25 April 2008 (CEST) The precise details are part of the agreement, but the figure should help. To be presented to and discussed by the QA group.
Scope --[[User:Jo|Jo]] 23:10, 25 April 2008 (CEST) The precise details are part of the agreement, but the figure should help. To be presented to and discussed by the QA group.
Line 39: Line 39:
[[#top|Go to top]]
[[#top|Go to top]]
== Scope ==
== Scope ==
-
The scope of an ITERMAG Contract Project is defined by the call for interest or call for tender which gives rise to the contract itself. It is then reduced, if necessary, by the Project Leadership and ultimately by the Steering Committee.
+
The scope of an ITERMAG Contract Project is defined by the call for interest or call for tender which gives rise to the contract itself. It is then reduced, if necessary, by the Consortium Programme Leadership and ultimately by the Steering Committee.
Status --[[User:Jo|Jo]] 19:23, 27 April 2008 (CEST)-- no more needed
Status --[[User:Jo|Jo]] 19:23, 27 April 2008 (CEST)-- no more needed
Line 46: Line 46:
== Schedule ==
== Schedule ==
The scheduling of a Contract Project is handled under Primavera using the following independent contract schedules:  
The scheduling of a Contract Project is handled under Primavera using the following independent contract schedules:  
-
* Consortium Project planning, for the activities of the full ITERMAG Consortium Project
 
* Magnetics construction planning, strongly linked to the ITER IO planning
* Magnetics construction planning, strongly linked to the ITER IO planning
-
* Contract Project planning, independently generated for each '''Contract Project''' and linked to the Consortium Project Planning
+
* Contract Project planning, independently generated for each '''Contract Project''' and linked to the Consortium Programme Planning
Status --[[User:Jo|Jo]] 19:23, 27 April 2008 (CEST) no more needed
Status --[[User:Jo|Jo]] 19:23, 27 April 2008 (CEST) no more needed
Line 61: Line 60:
* the contract risks
* the contract risks
   
   
-
An outline offer is then generated in collaboration with the Consortium Project Leadership. This offer is submitted to the Steering Committee for approval.
+
An outline offer is then generated in collaboration with the Consortium Programme Leadership. This offer is submitted to the Steering Committee for approval.
After approval by the Steering Committee:
After approval by the Steering Committee:
Line 78: Line 77:
[[#top|Go to top]]
[[#top|Go to top]]
== Quality ==
== Quality ==
-
The Contract Project functions respecting the Consortium Project Quality Plan. This Quality Plan presents the procedures and tools to ensure that the individual Contract Project Management Plan is correctly and traceably executed by the Contract Project Manager.  
+
The Contract Project functions respecting the Contract Project Quality Plan under the Consortium Programme Quality System. This Quality Plan presents the procedures and tools to ensure that the individual Contract Project Management Plan is correctly and traceably executed by the Contract Project Manager.  
Status --[[User:Jo|Jo]] 19:23, 27 April 2008 (CEST) Subset of the Consortium Project Quality Plan, no additional document required.
Status --[[User:Jo|Jo]] 19:23, 27 April 2008 (CEST) Subset of the Consortium Project Quality Plan, no additional document required.
Line 84: Line 83:
[[#top|Go to top]]
[[#top|Go to top]]
== Resource Management ==
== Resource Management ==
-
Human Resources are "assigned" to work for the ITERMAG Consortium and will either be allocated to the Consortium Project Leadership or to a specific Contract Project Manager.
+
Human Resources are "assigned" to work for the ITERMAG Consortium and will either be allocated to the Consortium Programme Leadership or to a specific Contract Project Manager.
Clear accounting of the allocated resources for a Contract Project will fall under "Finance".
Clear accounting of the allocated resources for a Contract Project will fall under "Finance".
Forward planning of the required and allocated resources will be generated by the Contract Project Manager.
Forward planning of the required and allocated resources will be generated by the Contract Project Manager.
Line 97: Line 96:
=== External communications ===
=== External communications ===
* Technical decisions: Client <--> Contract Project Leader, copied to Contract Project Team and Consortium Project Leadership and archived.
* Technical decisions: Client <--> Contract Project Leader, copied to Contract Project Team and Consortium Project Leadership and archived.
-
* Technical information exchanges: Client <--> Contract Project Leader, copied to Contract Project Team and Consortium Project Leadership and archived.
+
* Technical information exchanges: Client <--> Contract Project Leader, copied to Contract Project Team and Consortium Programme Leadership and archived.
=== Internal communications ===
=== Internal communications ===
-
* Consortium Project Leader --> Contract Project Manager, copied to Project Leadership and archived.
+
* Consortium Programme Leader --> Contract Project Manager, copied to Project Leadership and archived.
-
* Contract Project Manager --> Consortium Project Leader, coped to Consortium Project Leadership and archived.
+
* Contract Project Manager --> Consortium Programme Leader, coped to Consortium Project Leadership and archived.
Status --[[User:Jo|Jo]] 22:41, 25 April 2008 (CEST) The usage of the Wiki under development for ITERMAG is being evaluated as appropriate for archival. How to handle E-mail is under discussion.
Status --[[User:Jo|Jo]] 22:41, 25 April 2008 (CEST) The usage of the Wiki under development for ITERMAG is being evaluated as appropriate for archival. How to handle E-mail is under discussion.
Line 117: Line 116:
=== Contract condition changes ===
=== Contract condition changes ===
-
* Contract Project Manager --> Consortium Project Leader, Contract Condition Change is notified if performance, cost or schedule variations lead to conflict with the contract conditions. Consortium Project Leader assumes responsibility.
+
* Contract Project Manager --> Consortium Programme Leader, Contract Condition Change is notified if performance, cost or schedule variations lead to conflict with the contract conditions. Consortium Programme Leader assumes responsibility.
-
* Client --> Consortium Project Leader, Contract Condition Change is notified if technical changes are required by the client. Consortium Project Leader evaluates the impact of the changes and reports to Steering Committee with a proposed action.
+
* Client --> Consortium Programme Leader, Contract Condition Change is notified if technical changes are required by the client. Consortium Project Leader evaluates the impact of the changes and reports to Steering Committee with a proposed action.
=== Internal management changes ===
=== Internal management changes ===
* Member --> Steering Committee, Member reports any change in resources previously allocated.
* Member --> Steering Committee, Member reports any change in resources previously allocated.
-
Status --[[User:Jo|Jo]] 23:10, 25 April 2008 (CEST) The development of the change request system is intimately linked with the Quality Plan and appropriate procedures and forms will be proposed by the QA experts under request by the Consortium Project Leader.
+
Status --[[User:Jo|Jo]] 23:10, 25 April 2008 (CEST) The development of the change request system is intimately linked with the Quality Plan and appropriate procedures and forms will be proposed by the QA experts under request by the Consortium Programme Leader.
[[#top|Go to top]]
[[#top|Go to top]]
Line 134: Line 133:
Risks are assessed by:
Risks are assessed by:
* Contract Project Manager for a first technical and commercial view
* Contract Project Manager for a first technical and commercial view
-
* Consortium Project Leadership to ensure a common technical and commercial view
+
* Consortium Programme Leadership to ensure a common technical and commercial view
* Steering Committee to ensure a global financial and strategic view
* Steering Committee to ensure a global financial and strategic view

Revision as of 16:19, 15 May 2008

Contents

Generalities

The Contract Project Management Plan is a document that describes the Contract Project management system used by a contract manager.

The objective of the Contract Project Management Plan is do define the approach to be used by the Contract Project Manager to deliver the intended scope of the Contract Project.

The Contract Project Manager follows the Contract Project Management Plan following input from the Consortium Programme Leadership.


The Contract Project Management Plan includes the following main aspects:


We go through these proposed components one by one for ITERMAG to determine whether they should be part of the ITERMAG Contract Project Management Plan or not, and what the current status is.

Go to top

Structure

The Contract is structured as a Project, as a component of the Consortium Project Quality Plan.

File:Struc 001.gif

Contract Project Management

The Contract Project Management provides surveillance of a Contract Project. The Consortium Programme Leader then reports to the Consortium Steering Committee.

Contract Project Manager

Each call for tender gives rise to a "Contract Project" for which a Contract Project Manager is nominated by the Project Leadership. The Contract Project Manager develops a plan of action to generate an offer. In case of a contract being awarded, the Contract Project Manager is responsible for the correct execution of the Contract Project. The Contract Project Manager reports to the Consortium Programme Leader.

Scope --Jo 23:10, 25 April 2008 (CEST) The precise details are part of the agreement, but the figure should help. To be presented to and discussed by the QA group.

Go to top

Scope

The scope of an ITERMAG Contract Project is defined by the call for interest or call for tender which gives rise to the contract itself. It is then reduced, if necessary, by the Consortium Programme Leadership and ultimately by the Steering Committee.

Status --Jo 19:23, 27 April 2008 (CEST)-- no more needed

Go to top

Schedule

The scheduling of a Contract Project is handled under Primavera using the following independent contract schedules:

Status --Jo 19:23, 27 April 2008 (CEST) no more needed

Go to top

Tendering

The Contract Project Manager is responsible for creating a full response to a call for interest or a call for tender. This response for creating a Contract Project includes:

An outline offer is then generated in collaboration with the Consortium Programme Leadership. This offer is submitted to the Steering Committee for approval.

After approval by the Steering Committee:

The process for handling a call for interest or a call for tender is illustrated below. FIGURE

Go to top

Financial

The Contract Project Manager creates a contract spending curve when creating a draft offer. The Contract Project Manager is subsequently responsible for maintaining records of all the costs incurred by all Members, and on comparing them with the predicted spending curve. Deviations which suggest a significant final deviation from the original cost estimates (>5%) shall be immediately signalled to the Consortium Project Leader.

Go to top

Quality

The Contract Project functions respecting the Contract Project Quality Plan under the Consortium Programme Quality System. This Quality Plan presents the procedures and tools to ensure that the individual Contract Project Management Plan is correctly and traceably executed by the Contract Project Manager.

Status --Jo 19:23, 27 April 2008 (CEST) Subset of the Consortium Project Quality Plan, no additional document required.

Go to top

Resource Management

Human Resources are "assigned" to work for the ITERMAG Consortium and will either be allocated to the Consortium Programme Leadership or to a specific Contract Project Manager. Clear accounting of the allocated resources for a Contract Project will fall under "Finance". Forward planning of the required and allocated resources will be generated by the Contract Project Manager. Non-release of the required Human Resources is foreseen to be a major difficulty due to the extreme pressure on Human Resources in the Member Associates.

Status --Jo 22:35, 25 April 2008 (CEST) To be part of the Contract of Agreement, and to be reviewed in June.

Go to top

Communications

Communications are partially described under Project Structure, and include internal and external communications.

External communications

Internal communications

Status --Jo 22:41, 25 April 2008 (CEST) The usage of the Wiki under development for ITERMAG is being evaluated as appropriate for archival. How to handle E-mail is under discussion.

Go to top

Change Control

Change Control contains 3 elements:

Technical design changes

Contract condition changes

Internal management changes

Status --Jo 23:10, 25 April 2008 (CEST) The development of the change request system is intimately linked with the Quality Plan and appropriate procedures and forms will be proposed by the QA experts under request by the Consortium Programme Leader.

Go to top

Risk

Assessment and management of risk is an integral component of the contract assessment on a case by case basis. Risks include:

Risks are assessed by:

Decisions on risk as the authority of the Steereing Committee.

Go to top

Procurement

Procurement of external resources/material

Status --Jo 23:10, 25 April 2008 (CEST) Not yet considered.

Go to top