PL:Contract Management Plan
From ITERMAGwiki
m (JoPL:Contract Management Plan moved to PL:Contract Management Plan over redirect) |
|||
| Line 29: | Line 29: | ||
=== Contract Project Management === | === Contract Project Management === | ||
| - | The Contract Project Management provides surveillance of a Contract Project. The Consortium Programme Leader | + | The Contract Project Management provides surveillance of a Contract Project. The Contract Project Management is under the Consortium Programme Management. The Consortium Programme Leader reports to the Consortium Steering Committee. |
=== Contract Project Manager === | === Contract Project Manager === | ||
| Line 62: | Line 62: | ||
After approval by the Steering Committee: | After approval by the Steering Committee: | ||
| - | * a Contract Project Leader is named by the Steering Committee in collaboration with the Consortium | + | * a Contract Project Leader is named by the Steering Committee in collaboration with the Consortium Programme Leadership |
* a full commercial offer is established | * a full commercial offer is established | ||
* the offer is transmitted to the Steering Committee for final approval and submission to the client. | * the offer is transmitted to the Steering Committee for final approval and submission to the client. | ||
| Line 72: | Line 72: | ||
== Financial== | == Financial== | ||
The Contract Project Manager creates a contract spending curve when creating a draft offer. The Contract Project Manager is subsequently responsible for maintaining records of all the costs incurred by all Members, and on comparing them with the predicted spending curve. Deviations which suggest a significant final | The Contract Project Manager creates a contract spending curve when creating a draft offer. The Contract Project Manager is subsequently responsible for maintaining records of all the costs incurred by all Members, and on comparing them with the predicted spending curve. Deviations which suggest a significant final | ||
| - | deviation from the original cost estimates (>5%) shall be immediately signalled to the Consortium | + | deviation from the original cost estimates (>5%) shall be immediately signalled to the Consortium Programme Leader. |
[[#top|Go to top]] | [[#top|Go to top]] | ||
== Quality == | == Quality == | ||
| - | The Contract Project functions respecting the Contract Project Quality Plan under the Consortium Programme Quality System. This Quality Plan presents the procedures and tools to ensure that the individual Contract Project Management Plan is correctly and traceably executed by the Contract Project Manager. | + | The Contract Project functions respecting the Contract Project Quality Plan under the Consortium Programme Quality Management System. This Quality Plan presents the procedures and tools to ensure that the individual Contract Project Management Plan is correctly and traceably executed by the Contract Project Manager. |
| - | Status --[[User:Jo|Jo]] 19:23, 27 April 2008 (CEST) Subset of the Consortium | + | Status --[[User:Jo|Jo]] 19:23, 27 April 2008 (CEST) Subset of the Consortium Programme Quality Management System, no additional document required. |
[[#top|Go to top]] | [[#top|Go to top]] | ||
| Line 94: | Line 94: | ||
=== External communications === | === External communications === | ||
| - | * Technical decisions: Client <--> Contract Project Leader, copied to Contract Project Team and Consortium | + | * Technical decisions: Client <--> Contract Project Leader, copied to Contract Project Team and Consortium Programme Leadership and archived. |
* Technical information exchanges: Client <--> Contract Project Leader, copied to Contract Project Team and Consortium Programme Leadership and archived. | * Technical information exchanges: Client <--> Contract Project Leader, copied to Contract Project Team and Consortium Programme Leadership and archived. | ||
=== Internal communications === | === Internal communications === | ||
* Consortium Programme Leader --> Contract Project Manager, copied to Project Leadership and archived. | * Consortium Programme Leader --> Contract Project Manager, copied to Project Leadership and archived. | ||
| - | * Contract Project Manager --> Consortium Programme Leader, coped to Consortium | + | * Contract Project Manager --> Consortium Programme Leader, coped to Consortium Programme Leadership and archived. |
Status --[[User:Jo|Jo]] 22:41, 25 April 2008 (CEST) The usage of the Wiki under development for ITERMAG is being evaluated as appropriate for archival. How to handle E-mail is under discussion. | Status --[[User:Jo|Jo]] 22:41, 25 April 2008 (CEST) The usage of the Wiki under development for ITERMAG is being evaluated as appropriate for archival. How to handle E-mail is under discussion. | ||
| Line 111: | Line 111: | ||
=== Technical design changes === | === Technical design changes === | ||
| - | * Client <--> | + | * Client <--> Contract Project Manager, Design Change Request and cost/schedule impact signed on both sides after agreement, copied to Consortium Programme Leader and archived. The DCR clearly states all interfaces affected by the change. Consortium Programme Leader rejects or approves change and signs. If impact on cost-schedule is significant (TBD) final decision is deferred to Steering Committee by Consortium Programme Leader. The Design Change Decision is then archived. |
| - | * Consortium Member --> Contract Project Manager, Design Change Proposal signed on both sides after agreement, to be submitted to Consortium | + | * Consortium Member --> Contract Project Manager, Design Change Proposal signed on both sides after agreement, to be submitted to Consortium Programme Manager for transmission to client if Contract Project Manager agrees. |
=== Contract condition changes === | === Contract condition changes === | ||
* Contract Project Manager --> Consortium Programme Leader, Contract Condition Change is notified if performance, cost or schedule variations lead to conflict with the contract conditions. Consortium Programme Leader assumes responsibility. | * Contract Project Manager --> Consortium Programme Leader, Contract Condition Change is notified if performance, cost or schedule variations lead to conflict with the contract conditions. Consortium Programme Leader assumes responsibility. | ||
| - | * Client --> Consortium Programme Leader, Contract Condition Change is notified if technical changes are required by the client. Consortium | + | * Client --> Consortium Programme Leader, Contract Condition Change is notified if technical changes are required by the client. Consortium Programme Leader evaluates the impact of the changes and reports to Steering Committee with a proposed action. |
=== Internal management changes === | === Internal management changes === | ||
Revision as of 11:00, 22 May 2008
Contents |
Generalities
The Contract Project Management Plan is a document that describes the Contract Project management system used by a contract manager.
The objective of the Contract Project Management Plan is do define the approach to be used by the Contract Project Manager to deliver the intended scope of the Contract Project.
The Contract Project Manager follows the Contract Project Management Plan following input from the Consortium Programme Leadership.
The Contract Project Management Plan includes the following main aspects:
- Contract Structure;
- Scope Management;
- Schedule Management;
- Financial Management;
- Quality Management;
- Resource Management for resources like people, tools and others;
- Communications management;
- Contract Change Management;
- Risk Management; and
- Procurement Management
We go through these proposed components one by one for ITERMAG to determine whether they should be part of the ITERMAG Consortium Programme Management Plan or not, and what the current status is.
Structure
The Contract is structured as a Project, as a component of the Consortium Project Quality Plan.
Contract Project Management
The Contract Project Management provides surveillance of a Contract Project. The Contract Project Management is under the Consortium Programme Management. The Consortium Programme Leader reports to the Consortium Steering Committee.
Contract Project Manager
Each call for tender gives rise to a "Contract Project" for which a Contract Project Manager is nominated by the Project Leadership. The Contract Project Manager develops a plan of action to generate an offer. In case of a contract being awarded, the Contract Project Manager is responsible for the correct execution of the Contract Project. The Contract Project Manager reports to the Consortium Programme Leader.
Scope --Jo 23:10, 25 April 2008 (CEST) The precise details are part of the agreement, but the figure should help. To be presented to and discussed by the QA group.
Scope
The scope of an ITERMAG Contract Project is defined by the call for interest or call for tender which gives rise to the contract itself. It is then reduced, if necessary, by the Consortium Programme Leadership and ultimately by the Steering Committee.
Status --Jo 19:23, 27 April 2008 (CEST)-- no more needed
Schedule
The scheduling of a Contract Project is handled under Primavera using the following independent contract schedules:
- Magnetics construction planning, strongly linked to the ITER IO planning
- Contract Project planning, independently generated for each Contract Project and linked to the Consortium Programme Planning
Status --Jo 19:23, 27 April 2008 (CEST) no more needed
Tendering
The Contract Project Manager is responsible for creating a full response to a call for interest or a call for tender. This response for creating a Contract Project includes:
- the resource requirements for each Member
- a back-to-back agreement between Members to agree and guarantee these resources
- the contract schedule
- the contract costs for each Member
- the contract risks
An outline offer is then generated in collaboration with the Consortium Programme Leadership. This offer is submitted to the Steering Committee for approval.
After approval by the Steering Committee:
- a Contract Project Leader is named by the Steering Committee in collaboration with the Consortium Programme Leadership
- a full commercial offer is established
- the offer is transmitted to the Steering Committee for final approval and submission to the client.
The process for handling a call for interest or a call for tender is illustrated below.
Financial
The Contract Project Manager creates a contract spending curve when creating a draft offer. The Contract Project Manager is subsequently responsible for maintaining records of all the costs incurred by all Members, and on comparing them with the predicted spending curve. Deviations which suggest a significant final deviation from the original cost estimates (>5%) shall be immediately signalled to the Consortium Programme Leader.
Quality
The Contract Project functions respecting the Contract Project Quality Plan under the Consortium Programme Quality Management System. This Quality Plan presents the procedures and tools to ensure that the individual Contract Project Management Plan is correctly and traceably executed by the Contract Project Manager.
Status --Jo 19:23, 27 April 2008 (CEST) Subset of the Consortium Programme Quality Management System, no additional document required.
Resource Management
Human Resources are "assigned" to work for the ITERMAG Consortium and will either be allocated to the Consortium Programme Leadership or to a specific Contract Project Manager. Clear accounting of the allocated resources for a Contract Project will fall under "Finance". Forward planning of the required and allocated resources will be generated by the Contract Project Manager. Non-release of the required Human Resources is foreseen to be a major difficulty due to the extreme pressure on Human Resources in the Member Associates.
Status --Jo 22:35, 25 April 2008 (CEST) To be part of the Contract of Agreement, and to be reviewed in June.
Communications
Communications are partially described under Project Structure, and include internal and external communications.
External communications
- Technical decisions: Client <--> Contract Project Leader, copied to Contract Project Team and Consortium Programme Leadership and archived.
- Technical information exchanges: Client <--> Contract Project Leader, copied to Contract Project Team and Consortium Programme Leadership and archived.
Internal communications
- Consortium Programme Leader --> Contract Project Manager, copied to Project Leadership and archived.
- Contract Project Manager --> Consortium Programme Leader, coped to Consortium Programme Leadership and archived.
Status --Jo 22:41, 25 April 2008 (CEST) The usage of the Wiki under development for ITERMAG is being evaluated as appropriate for archival. How to handle E-mail is under discussion.
Change Control
Change Control contains 3 elements:
Technical design changes
- Client <--> Contract Project Manager, Design Change Request and cost/schedule impact signed on both sides after agreement, copied to Consortium Programme Leader and archived. The DCR clearly states all interfaces affected by the change. Consortium Programme Leader rejects or approves change and signs. If impact on cost-schedule is significant (TBD) final decision is deferred to Steering Committee by Consortium Programme Leader. The Design Change Decision is then archived.
- Consortium Member --> Contract Project Manager, Design Change Proposal signed on both sides after agreement, to be submitted to Consortium Programme Manager for transmission to client if Contract Project Manager agrees.
Contract condition changes
- Contract Project Manager --> Consortium Programme Leader, Contract Condition Change is notified if performance, cost or schedule variations lead to conflict with the contract conditions. Consortium Programme Leader assumes responsibility.
- Client --> Consortium Programme Leader, Contract Condition Change is notified if technical changes are required by the client. Consortium Programme Leader evaluates the impact of the changes and reports to Steering Committee with a proposed action.
Internal management changes
- Member --> Steering Committee, Member reports any change in resources previously allocated.
Status --Jo 23:10, 25 April 2008 (CEST) The development of the change request system is intimately linked with the Quality Plan and appropriate procedures and forms will be proposed by the QA experts under request by the Consortium Programme Leader.
Risk
Assessment and management of risk is an integral component of the contract assessment on a case by case basis. Risks include:
- Unable to deliver the scope/performance of the contract
- Unable to deliver the scheduling of the contract
- Unable to meet the estimated value of the contract
Risks are assessed by:
- Contract Project Manager for a first technical and commercial view
- Consortium Programme Leadership to ensure a common technical and commercial view
- Steering Committee to ensure a global financial and strategic view
Decisions on risk as the authority of the Steereing Committee.
Procurement
Procurement of external resources/material
Status --Jo 23:10, 25 April 2008 (CEST) Not yet considered.