== Generalities ==
== Generalities ==
-
The '''Contract Project Management Plan''' is a document that describes the '''Contract Project''' management system used by a Contract Project Manager.  
+
The '''Contract Project Management Plan''' is a document that describes the '''Contract Project''' management system used by a '''Contract Project Manager'''.  
The objective of the '''Contract Project Management Plan''' is do define the approach to be used by the Contract Project Manager to deliver the intended scope of the Contract Project.
The objective of the '''Contract Project Management Plan''' is do define the approach to be used by the Contract Project Manager to deliver the intended scope of the Contract Project.
Line 24: Line 24:
[[#top|Go to top]]
[[#top|Go to top]]
== Contract Project Management Structure ==
== Contract Project Management Structure ==
-
The Contract is structured as a Project, and is a component of the Consortium Programme Quality Plan.
+
Eeach Consortium Contract is structured as a '''Project''', and is a component of the Consortium Structure, as shown in the following figure.
[[image:Structure.gif]]
[[image:Structure.gif]]
=== Context ===
=== Context ===
-
The Contract Project Management provides surveillance of a Contract Project. The Contract Project Management is under the Consortium Programme Management. The Consortium Programme Leader reports to the Consortium Steering Committee.
+
The Contract Project Management provides surveillance of a Contract Project. The Contract Project Management functions under the Consortium Programme Leadership. The Consortium Programme Leader reports to the Consortium Steering Committee.
=== Contract Project Manager ===
=== Contract Project Manager ===
Each call for interest gives rise to a "Contract Project" for which a Contract Project Manager is nominated by the Consortium Programme Leadership. The Contract Project Manager develops a plan of action to generate an offer. In case of a contract being awarded, the Contract Project Manager is responsible for the correct execution of the Contract Project. The Contract Project Manager reports to the Consortium Programme Leader.
Each call for interest gives rise to a "Contract Project" for which a Contract Project Manager is nominated by the Consortium Programme Leadership. The Contract Project Manager develops a plan of action to generate an offer. In case of a contract being awarded, the Contract Project Manager is responsible for the correct execution of the Contract Project. The Contract Project Manager reports to the Consortium Programme Leader.
-
Scope --[[User:Jo|Jo]] 23:10, 25 April 2008 (CEST) The precise details are part of the agreement, but the figure should help. To be presented to and discussed by the QA group.
 
[[#top|Go to top]]
[[#top|Go to top]]
== Scope ==
== Scope ==
-
The scope of an ITERMAG Contract Project is defined by the call for interest or call for tender which gives rise to the contract itself. It is then reduced, if necessary, by the Consortium Programme Leadership and ultimately by the Steering Committee.
+
The scope of an ITERMAG Contract Project is defined by a call for interest or call for tender which gives rise to the contract or F4E grant itself. Both are referred to as "Contracts". It is then reduced, if necessary, by the Consortium Programme Leadership and ultimately by the Steering Committee.
-
 
+
-
Status --[[User:Jo|Jo]] 19:23, 27 April 2008 (CEST)-- no more needed
+
[[#top|Go to top]]
[[#top|Go to top]]
Line 47: Line 44:
* Magnetics construction planning, strongly linked to the ITER IO planning
* Magnetics construction planning, strongly linked to the ITER IO planning
* Contract Project planning, independently generated for each '''Contract Project''' and linked to the Consortium Programme Planning
* Contract Project planning, independently generated for each '''Contract Project''' and linked to the Consortium Programme Planning
-
 
-
Status --[[User:Jo|Jo]] 19:23, 27 April 2008 (CEST) no more needed
 
[[#top|Go to top]]
[[#top|Go to top]]
== Tendering ==
== Tendering ==
-
The Contract Project Manager is responsible for creating a full response to a call for interest or a call for tender. This response for creating a Contract Project includes:
+
The Consortium Programme Leadership is initially responsible for creating a proposal for responding to a call for interest or a call for tender. This Outline Offer includes:
* the resource requirements for each Member
* the resource requirements for each Member
* a back-to-back agreement between Members to agree and guarantee these resources
* a back-to-back agreement between Members to agree and guarantee these resources
Line 59: Line 54:
* the contract risks
* the contract risks
   
   
-
An outline offer is then generated in collaboration with the Consortium Programme Leadership. This offer is submitted to the Steering Committee for approval.
+
This Outline Offer is submitted to the Steering Committee for modification or approval.
After approval by the Steering Committee:
After approval by the Steering Committee:
-
* a Contract Project Leader is named by the Steering Committee in collaboration with the Consortium Programme Leadership
+
* a Contract Project Manager is confirmed by the Steering Committee in collaboration with the Consortium Programme Leadership
* a full commercial offer is established
* a full commercial offer is established
-
* the offer is transmitted to the Steering Committee for final approval and submission to the client.
+
* the offer is transmitted to the Steering Committee for final approval and ultimately submission to the client.
-
The process for handling a call for interest or a call for tender is illustrated below.
+
The process for handling a call for interest or a call for tender is illustrated in the figure below.
[[image:ProcCallten.gif]]
[[image:ProcCallten.gif]]
Line 73: Line 68:
The Contract Project Manager creates a contract spending curve when creating a draft offer. The Contract Project Manager is subsequently responsible for maintaining records of all the costs incurred by all Members, and on comparing them with the predicted spending curve. Deviations which suggest a significant final
The Contract Project Manager creates a contract spending curve when creating a draft offer. The Contract Project Manager is subsequently responsible for maintaining records of all the costs incurred by all Members, and on comparing them with the predicted spending curve. Deviations which suggest a significant final
deviation from the original cost estimates (>5%) shall be immediately signalled to the Consortium Programme Leader.
deviation from the original cost estimates (>5%) shall be immediately signalled to the Consortium Programme Leader.
 +
 +
Splitting of the revenu from a Contract will be on an uniform basis according to the Contract of Association.
 +
[[#top|Go to top]]
[[#top|Go to top]]
== Quality ==
== Quality ==
The Contract Project functions respecting the Contract Project Quality Plan under the Consortium Programme Quality Management System. This Quality Plan presents the procedures and tools to ensure that the individual Contract Project Management Plan is correctly and traceably executed by the Contract Project Manager.  
The Contract Project functions respecting the Contract Project Quality Plan under the Consortium Programme Quality Management System. This Quality Plan presents the procedures and tools to ensure that the individual Contract Project Management Plan is correctly and traceably executed by the Contract Project Manager.  
-
 
-
Status --[[User:Jo|Jo]] 19:23, 27 April 2008 (CEST) Subset of the Consortium Programme Quality Management System, no additional document required.
 
[[#top|Go to top]]
[[#top|Go to top]]
Line 85: Line 81:
Clear accounting of the allocated resources for a Contract Project will fall under "Finance".
Clear accounting of the allocated resources for a Contract Project will fall under "Finance".
Forward planning of the required and allocated resources will be generated by the Contract Project Manager.
Forward planning of the required and allocated resources will be generated by the Contract Project Manager.
-
Non-release of the required Human Resources is foreseen to be a major difficulty due to the extreme pressure on Human Resources in the Member Associates.
+
Non-release of the required Human Resources is foreseen to be a major difficulty due to the extreme pressure on Human Resources in the Members.
-
 
+
-
Status --[[User:Jo|Jo]] 22:35, 25 April 2008 (CEST) To be part of the Contract of Agreement, and to be reviewed in June.
+
[[#top|Go to top]]
[[#top|Go to top]]
Line 94: Line 88:
=== External communications ===
=== External communications ===
-
* Technical decisions: Client <--> Contract Project Leader, copied to Contract Project Team and Consortium Programme Leadership and archived.
+
* Technical decisions: Client <--> Contract Project Manager, copied to Contract Project Team and Consortium Programme Leadership and archived.
-
* Technical information exchanges: Client <--> Contract Project Leader, copied to Contract Project Team and Consortium Programme Leadership and archived.
+
* Technical information exchanges: Client <--> Contract Project Manager, copied to Contract Project Team and Consortium Programme Leadership and archived.
=== Internal communications ===
=== Internal communications ===
-
* Consortium Programme Leader --> Contract Project Manager, copied to Project Leadership and archived.
+
* Consortium Programme Leader --> Contract Project Manager, copied to Consortium Project Leadership and archived.
* Contract Project Manager --> Consortium Programme Leader, coped to Consortium Programme Leadership and archived.
* Contract Project Manager --> Consortium Programme Leader, coped to Consortium Programme Leadership and archived.

Revision as of 17:08, 16 June 2008

Contents

Generalities

The Contract Project Management Plan is a document that describes the Contract Project management system used by a Contract Project Manager.

The objective of the Contract Project Management Plan is do define the approach to be used by the Contract Project Manager to deliver the intended scope of the Contract Project.

The Contract Project Manager follows the Contract Project Management Plan following input from the Consortium Programme Leadership.

The Contract Project Management Plan includes the following main aspects:


We go through these proposed components one by one for ITERMAG to determine whether they should be part of the ITERMAG Consortium Programme Management Plan or not, and what the current status is.

Go to top

Contract Project Management Structure

Eeach Consortium Contract is structured as a Project, and is a component of the Consortium Structure, as shown in the following figure.

Structure.gif

Context

The Contract Project Management provides surveillance of a Contract Project. The Contract Project Management functions under the Consortium Programme Leadership. The Consortium Programme Leader reports to the Consortium Steering Committee.

Contract Project Manager

Each call for interest gives rise to a "Contract Project" for which a Contract Project Manager is nominated by the Consortium Programme Leadership. The Contract Project Manager develops a plan of action to generate an offer. In case of a contract being awarded, the Contract Project Manager is responsible for the correct execution of the Contract Project. The Contract Project Manager reports to the Consortium Programme Leader.


Go to top

Scope

The scope of an ITERMAG Contract Project is defined by a call for interest or call for tender which gives rise to the contract or F4E grant itself. Both are referred to as "Contracts". It is then reduced, if necessary, by the Consortium Programme Leadership and ultimately by the Steering Committee.

Go to top

Schedule

The scheduling of a Contract Project is handled under Primavera using the following independent contract schedules:

Go to top

Tendering

The Consortium Programme Leadership is initially responsible for creating a proposal for responding to a call for interest or a call for tender. This Outline Offer includes:

This Outline Offer is submitted to the Steering Committee for modification or approval.

After approval by the Steering Committee:

The process for handling a call for interest or a call for tender is illustrated in the figure below. ProcCallten.gif

Go to top

Financial

The Contract Project Manager creates a contract spending curve when creating a draft offer. The Contract Project Manager is subsequently responsible for maintaining records of all the costs incurred by all Members, and on comparing them with the predicted spending curve. Deviations which suggest a significant final deviation from the original cost estimates (>5%) shall be immediately signalled to the Consortium Programme Leader.

Splitting of the revenu from a Contract will be on an uniform basis according to the Contract of Association.


Go to top

Quality

The Contract Project functions respecting the Contract Project Quality Plan under the Consortium Programme Quality Management System. This Quality Plan presents the procedures and tools to ensure that the individual Contract Project Management Plan is correctly and traceably executed by the Contract Project Manager.

Go to top

Resource Management

Human Resources are "assigned" to work for the ITERMAG Consortium and will either be allocated to the Consortium Programme Leadership or to a specific Contract Project Manager. Clear accounting of the allocated resources for a Contract Project will fall under "Finance". Forward planning of the required and allocated resources will be generated by the Contract Project Manager. Non-release of the required Human Resources is foreseen to be a major difficulty due to the extreme pressure on Human Resources in the Members.

Go to top

Communications

Communications are partially described under Project Structure, and include internal and external communications.

External communications

Internal communications

Status --Jo 22:41, 25 April 2008 (CEST) The usage of the Wiki under development for ITERMAG is being evaluated as appropriate for archival. How to handle E-mail is under discussion.

Go to top

Change Control

Change Control contains 3 elements:

Technical design changes

Contract condition changes

Internal management changes

Status --Jo 23:10, 25 April 2008 (CEST) The development of the change request system is intimately linked with the Quality Plan and appropriate procedures and forms will be proposed by the QA experts under request by the Consortium Programme Leader.

Go to top

Risk

Assessment and management of risk is an integral component of the contract assessment on a case by case basis. Risks include:

Risks are assessed by:

Decisions on risk as the authority of the Steereing Committee.

Go to top

Procurement

Procurement of external resources/material

Status --Jo 23:10, 25 April 2008 (CEST) Not yet considered.